BtMData — Energía y compliance para centros de datos
    Rivabellosa

    Merlin Edged BIL02

    Verified profile of Merlin Edged BIL02 (Merlin Edged), a 48 MW data centre in Rivabellosa, Spain: mapped location, grid context and nearby renewables.

    MW

    48

    Substations <25 km

    —

    Renewables <25 km

    —

    Renewable MW nearby

    —

    Could your asset host a data centre?

    Indicative grid, energy and competition screening. Two queries per account; not a grid connection study.

    Rivabellosa, Spain
    Assess my asset

    Published MW and IT load have different scopes. A nearby substation confirms neither connection nor available capacity; check status and figures against their sources.

    Technical data

    Published capacity

    48 MW

    Year

    Not published

    Operator

    Merlin Edged

    Grid connection

    No mapped substation within 25 km

    BtMData grid mapping

    Fibre latency (physical estimate)

    ~3.7 ms RTT → Madrid (265 km)

    Computed: geodesic distance / 200 km·ms⁻¹

    Current ambient temperature

    …

    Live weather measurement

    Latency is a physical lower-bound estimate, not a real network measurement.

    Connectivity: network and transport

    Nearby infrastructure from OpenStreetMap, queried live.

    Loading…

    Data centre record

    Operator / developerMerlin Edged
    Published capacity48 MW
    CityRivabellosa
    CountrySpain
    Address—
    Coordinates42.72556, -2.90765
    Year—
    StatusUnder construction
    PhaseSecond building: latest official construction evidence found, 17 September 2025. The 3 December 2024 inauguration refers to the first building, not BIL02.
    Expected year—
    IT load—
    Capacity note48 MW planned for the second building, according to MERLIN (17 September 2025), without an explicit IT/utility basis. The announcement describes construction; current operation is unconfirmed. It is part of the 118 MW campus described in that update; do not add these overlapping scopes. Reviewed 25 October 2026.
    PUE—
    Energy type—
    Renewable energy—
    Energy note—
    Certifications—
    Certification note—
    Record last reviewed25/10/2026

    We only publish verifiable data. Anything the operator does not publish shows as “—”; it is never estimated.

    Links for Merlin Edged BIL02

    No source link is recorded for this site.Open in maps
    Assess an asset with GridPass